MBON screen progress 14.11.2026

on Saturday, November 14th, 2026 10:04 | by

MBON screen progress update 14.11.2026: A genotype finishes at significant. Just 11 flies left to measure before screen is finally complete.

Gustatory preference/Salt avoidance

on Thursday, November 12th, 2026 2:33 | by

Two-choice assay, 1.5M NaCl, 30 larvae/N, 20N/group, tests were performed blind; Experimental cross: SS02163>UAS-ChR2-XXL, control crosses: SS02163>w1118, w1118>UAS-ChR2-XXL

MBON screen progress 26.10.2026

on Monday, October 26th, 2026 10:10 | by

MBON screen progress 19.10.2026

on Monday, October 19th, 2026 11:48 | by

MBON screen 12.10.2026

on Monday, October 12th, 2026 1:00 | by

MBON screen update 12.10.2026, after removing flies measured while laser was too strong

MBON screen progress 5.10.2026

on Monday, October 5th, 2026 1:02 | by

MBON screen progress 21.09.2026

on Monday, September 21st, 2026 12:50 | by

MBON screen progress update 21.09.2026: Due to RIGeL summer school last week, I was only able to run two experiments, obtaining five flies, two of which had to be cut due to quality control.

MBON screen progress

on Monday, July 27th, 2026 12:43 | by

MBON screen progress 29.06.2026

on Monday, June 29th, 2026 9:50 | by

MBON Screen progress 01.06.2026

on Monday, June 1st, 2026 12:59 | by